LIVE PROJECTImplement a blended service operation

S2C 505 ยท FROM DISCOVERY TO STABILIZATION

How does an S2C implementation unfold?

Join a fictional industrial-service company as it implements one shared service spine for customer-site field work and in-house repair. The project keeps entitlement, technical history, execution evidence, billing, and service economics connected.

01

PROJECT PHASE

Discover

Define the service promise and operating reality

What the team does

Meet Customer Service, workshop, field operations, planning, inventory, Sales, Finance, Quality, IT, and mobile users. Capture products, installed base, channels, SLAs, warranties, contracts, charging models, locations, volumes, exceptions, and measures.

S2C project moment

Apex Industrial Services repairs major motor failures at its depot while technicians resolve smaller faults at customer sites.

Evidence to leave behind

Approved scope, stakeholder map, service catalog, volumes, pain points, assumptions, measures, and open questions.

02

PROJECT PHASE

Fit to standard

Classify service cases before designing documents

What the team does

Demonstrate the common request-to-cash spine, then classify real cases into remote support, field visit, or depot repair. Preserve only differences required by value, risk, regulation, or customer promise.

S2C project moment

The first release includes field and depot work; remote diagnostics is captured as a request activity, while subcontracted repair remains later scope.

Evidence to leave behind

Fit decisions, execution-model rules, gaps, owners, acceptance criteria, and decision log.

03

PROJECT PHASE

Design

Connect common controls to branch-specific evidence

What the team does

Define service organization, customer and technical-object identity, entitlement, dates, statuses, parts, custody, scheduling, mobile evidence, acceptance, billing, accounting, migration, roles, and reporting.

S2C project moment

Both paths share warranty and contract determination; depot design adds customer-equipment custody, while field design adds dispatch and technician stock.

Evidence to leave behind

Signed process design, data model, status model, interface contracts, role concept, billing rules, and end-to-end test conditions.

04

PROJECT PHASE

Configure

Build the shared spine before the branches

What the team does

Configure the minimum common scenario first, then depot and field dependencies in controlled order. Record decisions beside settings and prepare realistic customers, equipment, contracts, resources, and stock.

S2C project moment

One serial-numbered motor can create either a depot repair order or a field visit while retaining the same customer, equipment, entitlement, cost, and service history.

Evidence to leave behind

Configuration workbook, dependency and transport sequence, master-data readiness, unit evidence, and unresolved defects.

05

PROJECT PHASE

Test

Prove both golden paths and their exceptions

What the team does

Run unit, string, integration, mobile/offline, authorization, regression, and user-acceptance tests. Reconcile custody or dispatch, parts, confirmations, acceptance, billing, cost, revenue, receivable, and cash.

S2C project moment

Depot testing includes estimate reapproval and a manufactured component. Field testing includes missing technician stock, a follow-up visit, offline confirmation, and customer signature.

Evidence to leave behind

Passed evidence, reconciliations, defect decisions, retest results, business acceptance, and residual risk.

06

PROJECT PHASE

Cut over

Make workshop and field operations production-ready

What the team does

Sequence transports, roles, customers, sites, equipment, installed base, warranties, contracts, prices, open service cases, workshop custody, technician stock, mobile devices, forms, interfaces, jobs, and reconciliation checkpoints.

S2C project moment

The team validates open depot equipment by serial number, counts technician stock, synchronizes mobile devices, and executes one controlled request-to-confirmation smoke test per branch.

Evidence to leave behind

Approved cutover plan, owners, timings, migrated totals, custody and stock reconciliation, contingency triggers, and go/no-go decision.

07

PROJECT PHASE

Go live & stabilize

Operate queues, resolve causes, and transfer ownership

What the team does

Monitor request intake, entitlement failures, SLA queues, workshop backlog, dispatch, mobile synchronization, parts differences, confirmations, billing blocks, accounting, and support demand. Preserve evidence before changing configuration.

S2C project moment

Billing blocks rise because field technicians omit acceptance on offline visits; the team corrects the form and operating procedure, retests synchronization, and clears affected orders with retained evidence.

Evidence to leave behind

Daily controls, service KPIs, resolved root causes, accepted backlog, support knowledge, ownership transfer, and stabilization exit.

THE CONNECTING CONTROL

Do not bill what entitlement and delivered-service evidence cannot explain

The rule must survive workshops, branch design, configuration, negative testing, migration, mobile operation, cutover, and production monitoring.

Service promiseEntitlement decisionDepot or field executionConfirmation & acceptanceBilling proofService learning
USE THE FULL PATHReturn when a project detail needs depth

Use S2C 101 for process language, 202 for service capabilities, 303 for the two execution models, and 404 for configuration dependencies and proof.

Open the S2C path