MTO 202 · SCHEDULE
How is a feasible MTO delivery date promised?
SAP evaluates component availability, procurement lead time, capacity, in-house production time, and final assembly scheduling.
How SAP controls it
ATP or advanced ATP, checking rules, scheduling margins, capacity integration, and product allocation shape confirmation.
Example
The requested date moves by three days because a configured component must be procured.