MODULE TOPICExplore the capabilities that make MTO work

MAKE TO ORDER · PROMISE

How is a feasible MTO delivery date promised?

The requested date is the customer ask; the confirmed schedule-line date is the system promise. ATP and MRP contribute to one end-to-end story, but they answer different questions.

PROCESS ROLE

Read the promise decision

ATP checks the eligible stock and receipt picture against included requirements to confirm quantity and date. It does not by itself create the production or procurement supply that may later be needed. MRP evaluates planning demand and creates proposals; it can change the supply picture that a later ATP or rescheduling process sees. Delivery scheduling adds material availability, production, loading and goods-issue timing. Product allocation, backorder processing, capacity integration and advanced ATP can be deliberate extensions, but they are not mandatory characteristics of an MTO promise.

DECISION MODEL

Separate the controls that determine the result

Each layer owns a different part of the MTO outcome. Diagnose the layer that made the decision.

ATP SCOPE

ATP scope

Checking group, checking rule, plant, included stocks, receipts, requirements and replenishment lead time determine confirmation.

SCHEDULING MODEL

Scheduling model

Calendars, transit, pick/pack, loading, goods issue, procurement and in-house production times explain the dates.

OPTIONAL PROMISE SERVICES

Optional promise services

Use allocation, backorder processing, aATP or capacity integration only when their business rules are approved and tested.

OPERATIONAL FLOW

What happens in SAP

Read the sequence as one connected business event, not as isolated transactions.

01REQUEST

Capture the customer ask

The schedule line records requested quantity and date.

02CHECK

Calculate ATP confirmation

ATP applies the checking group, rule and scope to eligible stock, receipts and competing requirements.

03SCHEDULE

Build fulfilment dates

Material availability, production, loading and goods-issue dates form the delivery schedule.

04REPLAN

Respond to change

Order changes or supply changes can require new MRP proposals, ATP confirmation or approved rescheduling.

DESIGN & CONTROL

What shapes the result

These controls work together; a locally correct setting can still produce the wrong end-to-end outcome.

ATP scope

Checking group, checking rule, plant, included stocks, receipts, requirements and replenishment lead time determine confirmation.

Scheduling model

Calendars, transit, pick/pack, loading, goods issue, procurement and in-house production times explain the dates.

Optional promise services

Use allocation, backorder processing, aATP or capacity integration only when their business rules are approved and tested.

DIAGNOSTIC EVIDENCE

What proves the result

Use document, planning, logistics and Finance evidence together; one screen rarely tells the full MTO story.

COMMERCIAL

Requested and confirmed schedule-line quantity/date, checking group/rule, ATP elements and competing requirements.

SUPPLY & EXECUTION

Material availability, production, loading and goods-issue dates; calendars and lead-time assumptions.

CHANGE & FINANCE

MRP proposals and exception messages, kept distinct from the ATP result.

MTO SCENARIO

Trace one customer requirement

A component shortage moves the confirmed date. ATP shows why the original date cannot be confirmed; MRP then creates or reschedules a customer-specific proposal. A later supply change can improve the confirmation, but the order retains both requested and confirmed evidence.

  • ATP result is not called MRP
  • Each date has an explanation
  • Rescheduling is controlled
CONTINUE THE PATHContinue to MTO 303

See how the customer reference moves across Sales, planning, production, inventory, delivery and Finance.