202
CAPABILITY TOPICExplore the building blocks that make PS work

PS 202 · CONTROL

How do planning, budgeting, and status differ?

Keep cost and revenue planning, approved budget, availability control, forecast, versions, and lifecycle status conceptually separate.

READ THE CAPABILITY

Keep plan, authority, forecast, and status distinct

Planning describes expected cost, revenue, dates, quantities, and resources. Budget is the approved spending authority; availability control tests consumption against that authority. Forecast explains where the project is now expected to finish, while status governs which actions are allowed.

These controls work together but answer different questions. A project can be within budget and still be late, released but underplanned, or forecast to overrun while current actuals remain low.

WORKING FLOW

From business decision to controlled evidence

Follow the capability through the records and decisions that make the result explainable.

01STEP 01

Build the plan

Estimate work, cost, revenue, dates, resources, commitments, and risks against the project structure.

02STEP 02

Approve authority

Set budget, releases, tolerances, funding conditions, and the owner accountable for exceptions.

03STEP 03

Control consumption

Compare commitments and actuals with available budget and block or escalate according to status and tolerance.

04STEP 04

Reforecast and close

Update expected completion, explain variance, reconcile residuals, and close only when control evidence agrees.

DIAGNOSTIC EVIDENCE

What should be traceable?

When the result looks wrong, start with the last trusted record and follow the owning boundary.

PLAN

Version, dates, planned cost or revenue, quantities, assumptions, and responsible planning owner.

AUTHORITY

Approved budget, release, availability result, tolerance, status, funding condition, and decision history.

OUTLOOK

Commitments, actuals, remaining work, forecast at completion, variance reason, and approved response.

SCENARIO

A project is on budget but forecast to miss the commissioning date

The control view keeps the favorable cost variance separate from the schedule risk. The owner updates remaining work and forecast, records the decision needed, and preserves budget authority rather than treating a low actual-cost balance as proof of healthy delivery.

  • Business rule and accountable owner are explicit
  • SAP object and source evidence remain connected
  • Exception or outcome is reconciled before closure

CORE MODEL

Three questions to resolve

A sound design makes ownership, control, and evidence explicit before configuration.

CONTINUE THE PATHContinue to PS 303

See how this capability changes across valid integration models.

Open patterns