MODULE TOPICExplore the capabilities that make P2M work

P2M 202 · STRUCTURE

What is a bill of materials—and when should an assembly be phantom?

A BOM defines the components and quantities needed to make a material. Phantom assemblies preserve a logical grouping but are exploded into their components rather than planned or produced as separate stock.

HOW IT WORKS

Finished-product demand becomes component demand

Demand for a finished product must eventually become demand for the materials needed to make it. The Bill of Materials provides this product structure, so one requirement for a finished material can create requirements for assemblies, components, and raw materials further down the product structure.

Concept flow: Finished-product demand → BOM explosion → component demand. Phantom assemblies can organize the structure while their components flow directly into higher-level planning.

CAPABILITY MODEL

Understand the input, decision, and result

Read the capability as a connected planning decision before moving into detailed SAP controls.

INPUT

Finished-product requirement

A requirement for the finished material establishes what the business wants to make.

STRUCTURE

BOM relationship

The valid BOM expresses which assemblies and components, in what quantities, support that material.

OUTPUT

Dependent demand

Planning can explode the structure into lower-level material requirements.

OPERATIONAL FLOW

How the capability performs

The sequence connects business need to a planning or execution result.

01SELECT

Choose the valid structure

Material, plant, usage, alternative, validity, and change context identify the BOM that applies.

02EXPLODE

Translate the requirement

The finished-product quantity is multiplied through the component relationships to create lower-level demand.

03DISTINGUISH

Read the assembly intent

A stocked or produced assembly remains a planning object; a phantom grouping organizes structure without creating separate stock.

04HAND OFF

Feed planning and execution

The resulting component requirements support MRP and later production-order construction.

DESIGN & CONTROL

What shapes the result

These controls work together; a locally correct setting can still produce the wrong planning outcome.

Structure validity

Usage, alternative BOM, validity dates, change numbers, and plant determine which structure applies.

Component meaning

Item category, quantity, scrap, and unit relationships determine how demand is translated.

Assembly policy

Make, buy, stock, or phantom treatment determines whether an assembly receives its own supply response.

DIAGNOSTIC EVIDENCE

What proves the result?

Use the business input, system objects, and resulting state together.

PRODUCT STRUCTURE

Material, plant, BOM header, components, quantities, units, and validity.

PLANNING RESULT

Finished-product requirement, dependent requirements, and the selected structure reference.

EXECUTION ALIGNMENT

Production order components and the BOM or production-version selection used for the run.

PLANNING MOMENT

A pump requires a seal kit, but the kit is never stocked or produced separately.

The BOM keeps the seal kit as a logical grouping while the valid phantom setting lets planning and the production order see the individual seals directly.

  • Structure is valid for the plant
  • Quantities explode correctly
  • Phantom intent is deliberate
  • Order components match planning

IN SAP

Simple representation

These are the main planning objects to recognize before moving into detailed controls.

CORE OBJECTS

Material · BOM header · BOM components · Quantity relationships

How SAP controls it

BOM usage, alternative BOMs, item categories, validity dates, change numbers, component quantities, and phantom-item settings determine which components planning and production use.

Example

A finished pump uses a phantom seal kit: MRP and the production order see its seals directly, without creating stock or a separate order for the kit.

CONTINUE THE PATHContinue to P2M 303