INTERMEDIATE PRACTICEUnderstand the control model before operating it

P2M 202 ยท PLANNING DETERMINATION

What determines a planning result?

MRP behaviour is inherited from demand, stock, master data, and planning rules. Read the determination stack before treating a planned order, date, quantity, or sourcing decision as an isolated error.

CONTROL CHAIN

Explain the result before changing it

  1. 01
    DemandInput
  2. 02
    Stock & receiptsNetting
  3. 03
    Material planningProposal
  4. 04
    BOM / routingCapacity
  5. 05
    ProposalRelease

CONSULTANT LENS

Questions that determine the outcome

Material planning parameters

MRP type, lot size, safety stock, planning time fence, lead times, and procurement type influence supply quantity, date, and form.

Production model

BOM, routing, production version, work center, and validity decide the structure and execution model that supply inherits.

Supply boundary

Procurement type, special procurement, and source decisions determine whether MRP creates in-house supply or hands the need to P2P.

P2M SCENARIO

A proposal is dated too late

Trace requirement date, lead times, scheduling, firming, and selected production model before changing the proposal.

  • Prove the requirement and stock position.
  • Identify the exact input that created the date.
  • Retest proposal and dependent requirements.
CONTINUE THE PATHApply the model in the P2M practitioner map

Use 303 for operational execution and 606 to diagnose a live failure.