LIVE PROJECTWalk through an implementation

O2C 505 ยท FROM DISCOVERY TO STABILIZATION

How does an O2C implementation unfold?

Join a fictional distribution company as one standard Order-to-Cash flow moves from workshop questions to production evidence. The walkthrough shows the work, decisions, compromises, and proof expected at each project phase.

01

PROJECT PHASE

Discover

Clarify the business problem

What the team does

Meet Sales, Customer Service, Warehouse, Finance, Credit, Tax, and IT. Capture channels, volumes, variants, pain points, controls, integrations, and measures of success.

O2C project moment

A distributor needs one standard stocked-product flow first; returns, intercompany, and third-party fulfilment remain later scope.

Evidence to leave behind

Approved scope, stakeholder map, process evidence, assumptions, and open questions.

02

PROJECT PHASE

Fit to standard

Challenge the current way of working

What the team does

Demonstrate standard O2C with realistic data. Separate legal or valuable differences from habits, workarounds, and preferences.

O2C project moment

The team accepts delivery-related billing but keeps credit-release approval because exposure policy requires it.

Evidence to leave behind

Fit decisions, gaps, owners, acceptance criteria, and a traceable decision log.

03

PROJECT PHASE

Design

Connect business decisions

What the team does

Define the target process, organization, master data, roles, controls, integrations, reporting, migration, and non-functional needs before changing isolated settings.

O2C project moment

The design connects sales area 1000/10/00, plant 1100, standard documents, pricing, ATP, credit, billing, and FI account determination.

Evidence to leave behind

Signed process design, configuration rationale, interface contracts, role concept, and end-to-end test conditions.

04

PROJECT PHASE

Configure

Build in dependency order

What the team does

Configure the smallest complete scenario, record each decision beside its setting, transport dependencies together, and prepare controlled test data.

O2C project moment

A sales order determines its item, schedule line, price, plant, shipping point, availability result, and credit response without structural overrides.

Evidence to leave behind

Configuration workbook, transport sequence, master-data readiness, unit evidence, and unresolved defects.

05

PROJECT PHASE

Test

Prove the business story

What the team does

Run unit, string, integration, regression, authorization, and user-acceptance tests. Reconcile quantities, values, statuses, documents, interfaces, and accounting.

O2C project moment

One order moves through delivery, PGI, billing, FI, payment, and clearing; stock, COGS, revenue, tax, and receivable postings reconcile.

Evidence to leave behind

Passed evidence, defect decisions, retest results, business acceptance, and known residual risk.

06

PROJECT PHASE

Cut over

Make production ready

What the team does

Sequence transports, roles, master data, prices, credit data, stock, open transactions, interfaces, jobs, forms, and reconciliation checkpoints. Rehearse timing and contingency decisions.

O2C project moment

The team loads customers and prices, validates stock and credit exposure, enables interfaces, and runs a controlled first-order smoke test.

Evidence to leave behind

Approved cutover plan, owners, timings, validation totals, contingency triggers, and go/no-go decision.

07

PROJECT PHASE

Go live & stabilize

Operate, learn, and hand over

What the team does

Monitor the document chain, business queues, interfaces, postings, jobs, and support demand. Triage by business impact and preserve evidence before changing configuration.

O2C project moment

A billing block affects a customer group; the team traces determination, corrects the cause, retests the chain, and documents the support pattern.

Evidence to leave behind

Daily controls, resolved root causes, accepted backlog, support knowledge, ownership transfer, and stabilization exit.

THE CONNECTING THREAD

One decision must survive every phase

A requirement is not complete because it appeared in workshop notes. It must remain traceable through design, configuration, test evidence, cutover preparation, and production support.

Business needFit decisionSystem designConfigurationTest proofProduction control
USE THE FULL PATHReturn when a project detail needs depth

Use O2C 101 for process language, 202 for module topics, 303 for execution, and 404 for configuration dependencies.

Open the O2C path