LIVE PROJECTDeliver a usable warehouse operating model

How does an EWM implementation unfold?

A warehouse implementation is ready when real users can execute normal and exceptional work with trusted stock, working devices, connected modules, and a support model—not merely when configuration reaches production.

  1. 01

    Discover the physical operation

    Walk North DC receiving, pallet putaway, replenishment, case picking, packing, staging, loading, inventory counting, and exception paths. Observe the 12,000-line daily rhythm, peak release times, RF devices, labels, and the run-up to the 17:00 carrier cut-off.

    Evidence Observed North DC process catalogue, baseline KPIs, risks, and owners

  2. 02

    Fit to standard and design

    Agree the North DC release scope: pallet inbound, case-pick outbound, RF roles, replenishment, packing and staging, carrier hand-off, document/status ownership, exception policy, master data, interfaces, and extension decisions.

    Evidence Signed North DC design decisions and acceptance evidence

  3. 03

    Build the minimum spine

    Configure the North DC warehouse structure, putaway and picking determination, replenishment, RF work creation, queues/resources, waves, packing, staging, exceptions, and required integrations for the representative pallet-inbound to case-pick dispatch flow.

    Evidence Transported configuration and controlled master data for the North DC spine

  4. 04

    Test physical and integrated reality

    Run role-based unit, string, integration, volume, RF-device, printer, authorization, reversal, recovery, and day-in-the-life tests against the North DC flow. Prove that peak waves can be picked, packed, staged, and handed to carriers before 17:00; rehearse short picks, damaged stock, and device loss.

    Evidence Defects resolved against traceable North DC expected results

  5. 05

    Prepare cutover

    Clean and load North DC warehouse master data; prepare stock, open deliveries, and HU/packaging data; sequence interfaces; validate RF devices and labels; train each shift; rehearse stock reconciliation and carrier cut-off containment; and define rollback decisions.

    Evidence Approved North DC cutover runbook and readiness gate

  6. 06

    Go live and stabilize

    Run a named North DC command cadence around stock reconciliation, interface queues, RF/device failures, task backlog, exception volume, wave progress, staging, and the 17:00 carrier cut-off. Stabilize through shift support until service, stock, and support KPIs meet agreed exit criteria.

    Evidence Stable North DC KPIs, support ownership, and accepted handover

Process and data

Process catalogue, product/packaging data, bins, HUs, stock attributes, owners, and change control.

Devices and automation

RF flows, scanners, printers, labels, network, MFS or equipment interfaces, monitoring, and fallback procedures.

Cross-module integration

MM, SD, PP, QM, TM, Finance, middleware, security, and support ownership with shared test evidence.

Operational readiness

Role-based training, supervisor routines, cut-off controls, exception playbooks, hypercare triage, and measurable exit criteria.