PRODUCTION SUPPORTRestore the live planning-and-production loop

P2M 606 · PRODUCTION SUPPORT

How do you support Plan to Make when planning or production goes wrong?

Work from the operational symptom to the first unreliable demand, supply, execution, inventory, or integration fact. A production order can expose a problem created earlier by demand, MRP, master data, or inventory feedback.

P2M LOOP

Trace from requirement to actual feedback

Find the last known-good transition before changing MRP parameters or production transactions.

  1. 01
    DemandNeed
  2. 02
    MRPNetting
  3. 03
    Planned supplyProposal
  4. 04
    Production orderExecution
  5. 05
    ExecutionActual
  6. 06
    Receipt & replanFeedback

SUPPORT OPERATING LOOP

Correct the owning planning or execution layer

01TRIAGE

State the impact

Record material, plant, requirement, expected and actual result, scope, and whether supply is late, short, excessive, or blocked.

02TRACE

Find the failed transition

Follow demand → MRP → proposal → order → components → confirmation → receipt → inventory → replan.

03CLASSIFY

Choose the cause family

Separate demand, master data, planning, execution, inventory, integration, and authorization or operational controls.

04RESOLVE

Use the smallest correction

Correct demand, master data, proposal, transaction, inventory, or boundary integration at the layer that caused the result.

05PROVE

Retest the loop

Validate quantity, date, make-or-buy, components, order status, actuals, receipt, inventory, and remaining demand.

06PREVENT

Turn repeats into signals

Use demand review, exception monitoring, BOM and routing governance, confirmation discipline, and inventory reconciliation.

FIRST P2M DECISION

Is the issue in the plan or in execution?

A planned order is proposed supply; a production order is committed execution. Do not solve an execution symptom by changing a global planning setting.

DEMAND VS SUPPLY

Compare valid demand with stock and existing receipts before deciding that MRP missed supply.

MASTER DATA VS TRANSACTION

BOM, routing, production version, work center, lead time, and procurement type can determine the result inherited by the order.

PLAN VS REALITY

Goods issue, confirmation, yield, scrap, and receipt determine whether the next MRP run sees reality.

P2M DIAGNOSTIC PLAYBOOKS

Follow the path that matches the symptom

01 · MRP did not create supply

Trace: demand → stock → existing receipts → MRP parameters → net requirement → proposal. Confirm a shortage actually exists in ERP.

02 · MRP created too much, too little, or the wrong date

Trace: demand quantity/date → stock and receipts → safety, lot size, lead times, scheduling, firming → proposal. Identify the assumption that produced the result.

03 · System chose make or buy incorrectly

Trace: requirement → procurement type and source decision → planned order or purchase requisition. Confirm the intended P2M/P2P boundary.

04 · Component requirement is wrong

Trace: finished requirement → planned/production order → BOM validity and quantity → dependent requirement. Check the selected production version.

05 · Production order cannot be released or executed

Trace: proposal → order → BOM, routing, work center, components, status, release, and authorization. Treat the order as the execution form of the plan.

06 · Goods issue, confirmation, or receipt is wrong

Trace: order requirement → available stock → issue → operation and yield/scrap → receipt → inventory. Decide whether the fault is physical evidence or planning requirement.

07 · Next MRP run still looks wrong

Trace: actual production → goods movements → inventory → open supply → remaining demand → MRP. Look for late feedback, stale proposals, or obsolete demand.

P2M SUPPORT MOMENT

MRP did not create the production expected

Do not start with MRP settings. Prove the requirement, stock, receipts, date, planning proposal, and make-or-buy decision; then correct the first unreliable fact and rerun the complete loop.

  • Preserve the material, plant, requirement, and expected result.
  • Do not change global planning parameters for one exception.
  • Validate the next planning cycle, not only the original message.
USE THE FULL PATHReturn to P2M when deeper context is needed

Use 101 for the lifecycle, 202 for planning and production capabilities, 303 for execution, and 404 for configuration proof.

Open the P2M path