LIVE PROJECTWalk through an implementation

H2R 505 ยท FROM DISCOVERY TO STABILIZATION

How does an H2R implementation unfold?

Join a fictional regional business as one controlled hire-to-pay-and-exit release moves from workforce questions to production evidence.

01

PROJECT PHASE

Discover

Clarify the people and compliance problem

What the team does

Meet HR, Payroll, Finance, IT, managers, security, privacy, and employee representatives. Capture populations, countries, policy, controls, integrations, and success measures.

H2R project moment

The first release is one country and salaried employees; time clocks, more payroll countries, and advanced talent remain later scope.

Evidence to leave behind

Approved scope, stakeholder map, data inventory, compliance assumptions, and open decisions.

02

PROJECT PHASE

Fit to standard

Challenge habits before building exceptions

What the team does

Demonstrate a standard lifecycle using realistic roles and policy. Separate legal or workforce-agreement needs from historical workarounds.

H2R project moment

The team accepts standard onboarding tasks but retains formal manager approval for compensation changes.

Evidence to leave behind

Fit decisions, gaps, policy owners, acceptance criteria, and a decision log.

03

PROJECT PHASE

Design

Connect people data to downstream consequences

What the team does

Define the system of record, organisation model, effective dating, permissions, workflows, payroll boundary, Finance posting, integrations, reporting, retention, and migration rules.

H2R project moment

Core people data has one owner; approved employee and compensation changes reach payroll; Finance receives reconciled payroll postings.

Evidence to leave behind

Signed design, data ownership matrix, role concept, interface contracts, and test conditions.

04

PROJECT PHASE

Configure

Build in dependency order

What the team does

Configure the smallest complete scenario, record each decision beside its business rule, deploy only project-owned changes, and prepare protected test data.

H2R project moment

A new hire determines organisation, manager, job, position, pay group, workflow, permissions, payroll eligibility, and Finance allocation without manual repair.

Evidence to leave behind

Configuration rationale, deployment sequence, data readiness, unit evidence, and defects.

05

PROJECT PHASE

Test

Prove the employee story, not isolated screens

What the team does

Run integration, security, payroll, migration, regression, and user-acceptance tests. Reconcile records, dates, approvals, results, interfaces, and accounting totals.

H2R project moment

One fictional worker is hired, paid, transferred, and exited. Pay, access, Finance posting, and retained history match policy.

Evidence to leave behind

Passed evidence, security exceptions, retest results, business acceptance, and residual risk.

06

PROJECT PHASE

Cut over

Make data and operations ready

What the team does

Sequence deployment, roles, employee and organisational data, payroll controls, interfaces, schedules, reconciliations, communications, and contingency decisions.

H2R project moment

The team validates employee counts and pay totals, enables integrations, confirms access, and runs a controlled new-hire smoke test.

Evidence to leave behind

Approved cutover plan, data totals, owners, timings, contingency triggers, and go/no-go decision.

07

PROJECT PHASE

Go live & stabilize

Operate, protect, and improve

What the team does

Monitor hire and change queues, interfaces, payroll results, posting reconciliation, security requests, and support demand. Preserve evidence before changing rules or data.

H2R project moment

A future-dated transfer misses payroll. The team traces the effective date and interface status, corrects the approved source, retests, and documents the support pattern.

Evidence to leave behind

Daily controls, root-cause records, accepted backlog, support knowledge, ownership transfer, and stabilization exit.

PRODUCTION-READY PROOF

Test complete worker stories and controlled failures

Regression is not a list of screens. Prove the business event, SuccessFactors record, data and Position, RBP, workflow, integration, and downstream business result together.

Data and worker scenarios

Test a historical worker with incomplete data, a newly mandatory field, future-dated change, rehire, and contractor extension.

Position and RBP scenarios

Test occupied and vacant Positions, manager change, temporary assignment, reporting-line change, permitted view and maintain access, denied access, and restricted populations.

Workflow scenarios

Test normal approval, unavailable approver, delegation, missing manager, rejection, and resubmission.

Integration scenarios

Test SuccessFactors and target success, target-processing failure, mapping error, authentication or certificate failure, endpoint outage, delayed run, and controlled reprocessing.

Cutover and hypercare

Validate legacy data, permissions, workflow and integration monitoring, high-risk lifecycle events, and known failure patterns before handing over to support.

THE CONNECTING THREAD

One people decision must remain accountable

A person-data change is not complete because a screen saved. Its policy basis, owner, effective date, approval, downstream result, and support trail must remain traceable.

  1. 01
    Policy needIntent
  2. 02
    Fit decisionScope
  3. 03
    Data and process designModel
  4. 04
    ConfigurationBuild
  5. 05
    Test proofEvidence
  6. 06
    Production controlOperate
CONTINUE THE PATHContinue to H2R 606

Move from implementation evidence into production diagnosis, ownership, and continuous improvement.